Dredging costs at West Bay harbour are £42,000 more than expected

Local News by Lottie Welch 18th Mar 2021  

Dredging costs at West Bay harbour have come in at £42,000 more than expected.

Harbours committee members were told that the estimated cost of £75,000 of dredging for the outer harbour had gone up to £117,000 by the time the invoice was submitted.

The increase in costs was not questioned by committee members.

The harbour is expected to finish the financial year with a £35,000 overspend.

Harbourmaster James Radcliffe told councillors that some mooring holders at both West Bay and Lyme Regis had decided not to return in the coming season – but their spaces were quickly being taken from those on the waiting list.

He said that commercial diving, mainly for scallops, had continued during the lockdown which had helped the harbour air bottle refill income. Commercial moorings at both harbours remained at full capacity.

At Lyme Regis dredging is due to start on April 6 while at West Bay piling work due to start this month is likely to be delayed until next season unless contractors are able to get underway in early April.

Mr Radcliffe said the work was largely for appearance so would not cause any safety issues if the work was delayed.

     

CHECK OUT OUR Jobs Section HERE!
bridport vacancies updated hourly!
Click here to see more: bridport jobs

Share:


50%

Easter Gifts
With Easter 2026 fast approaching on Sunday, 5th April, we’ve curated a handpicked selection of the top things to do this Easter across London and the UK.
£335.99 £167.5

54%

15-Bar Espresso Coffee Machine with Integrated Grinder & Steamer
Top Quality 15-Bar Espresso Coffee Machine with Integrated Grinder & Steamer - 2L Capacity, Sleek Black
£335.99 £154.1

50%

Stylish aluminium garden set with two spacious sofas, plush washable cushions, and matching tables.
from £599 £299.5

Sign-up for our FREE newsletter...

We want to provide bridport with more and more clickbait-free news.